Joetsu Line operating record for 11/2026
East Japan Railway Company (JR East)The figures are compiled from the service status feeds this site has received, and are not official statistics from the railway companies.
Tallied up to 11/23 22:16 (updated every 10 minutes).
Total time service was suspended: 4 h 31 min
Per-train delay records start on November 6, 2026 (East Japan Railway Company, Tobu Railway, Keio Corporation, Toei Subway).
Day-by-day overview
Breakdown by cause
Daily list
- Train cancellations 4:01〜18:06 No cause stated
- Delay 21:36〜11/22 0:03 Miyauchi〜Echigo-Yuzawa Waiting for connecting trains
- Train cancellations 6:47〜11/21 2:05 No cause stated
- Delay 11:20〜20:56 Nagaoka〜Minakami strong winds
- Suspended 13:49〜14:10 (20 min) Muikamachi〜Ishiuchi Checking an unusual noise
- Suspended 21:04〜21:22 (17 min) Minakami〜Tsuchitaru 熊と衝突
- Delay 21:39〜22:02 Tsuchitaru〜Echigo-Yuzawa 熊と衝突
- Suspended 15:03〜15:42 (38 min) Miyauchi〜Echigo-Kawaguchi 信号装置点検
- Suspended 15:41〜18:58 (3 h 16 min) Miyauchi〜Echigo-Kawaguchi、Miyauchi〜Koide 信号装置故障
- Some trains cancelled 18:57〜11/13 1:02 Nagaoka〜Minakami、Nagaoka〜Echigo-Yuzawa、Nagaoka〜Ishiuchi 信号装置故障
- Delay 21:41〜21:59 Echigo-Yuzawa〜Nagaoka 乗務員急病
- Some trains cancelled 6:47〜7:31 Echigo-Kawaguchi〜Nagaoka Level crossing safety check
- Some trains cancelled 13:37〜14:31 Minakami〜Shim-Maebashi Vehicle inspection
- Delay 23:38〜11/9 0:31 Shim-Maebashi〜Minakami Waiting for connecting trains
- Delay 20:07〜20:52 Shim-Maebashi〜Minakami Waiting for connecting trains
- Delay 12:30〜13:21 Shim-Maebashi〜Minakami Waiting for connecting trains
- Delay 17:08〜18:06 Minakami〜Numata、Numata〜Takasaki 熊と衝突
- Delay 22:21〜23:26 Shim-Maebashi〜Minakami Waiting for connecting trains
Delay certificates and alternative transport
Source: Public Transportation Open Data Center (ODPT) and each operator
ODPT, the Association for Open Data of Public Transportation, and the operators accept no responsibility for the accuracy or completeness of the content.